Secretary of Hanoi: Yen Xa project will ‘revive’ inner-city rivers

Avatar of Nick John By Nick John Feb28,2024 #Hanoi #project #Secretary
Secretary of Hanoi: Yen Xa project will 'revive' inner-city rivers 2
Secretary of Hanoi: Yen Xa project will 'revive' inner-city rivers 2

On the morning of February 28, Secretary of the Hanoi Party Committee Dinh Tien Dung inspected the progress of the Yen Xa wastewater treatment plant project in Thinh Liet commune, Thanh Tri district.

The plant has a capacity of 270,000 m3 per day and night, scheduled for trial operation in the second quarter of this year and completed in 2025, serving wastewater treatment in the districts of Ba Dinh, Cau Giay, Thanh Xuan, Dong Da, Hoang Mai,

Secretary of Hanoi Party Committee Dinh Tien Dung directly inspected the bidding package to build the Yen Xa wastewater plant.

Inspecting the construction site of the Lu River sewer system and wastewater treatment plant, Hanoi Secretary said that the city aims to have the urban wastewater treatment rate reach 50-55% by 2025 (currently only

`The project is not only meaningful in achieving wastewater treatment targets, serving nearly one million people in 6 districts and Thanh Tri district, but also contributes to cleaning important rivers of the Capital such as To Lich and Lu

Mr. Dung evaluated the construction progress of packages 1 and 2 (wastewater treatment plant, To Lich river sewer) very positively.

Secretary of Hanoi: Yen Xa project will 'revive' inner-city rivers

Yen Xa wastewater plant is expected to have trial operation in the second quarter of 2024.

To speed up the project progress, the Secretary of Hanoi requested the City People’s Committee to direct the Technical and Agricultural Infrastructure Project Management Board (investor) to coordinate with departments and branches to terminate the contract for package No. 3,

Reporting at the meeting, the representative of the Project Management Board said that up to now, the construction of the Yen Xa wastewater treatment plant has been basically completed, with trial operation expected in the second quarter.

The Yen Xa wastewater treatment plant was started in 2016, using Japanese ODA loans (JICA) with a total investment of more than 16,000 billion VND, expected to be completed in 2019, but had to be delayed twice to the next year.

Hanoi has 5 rivers that are also the main drainage channels of the inner city area including To Lich, Lu, Set, Kim Nguu and Nhue rivers.